HASUH Pump Gate®, completed in Naju-si, Jeonnam-do, Korea

Project               : Youngsan River Pump Station
Pump Capacity  : Ф900mm x 110cmm x 6.5mH x 3ea
Contract Period : 2010. 11.19 ~ 2012. 02. 28
Location            : Youngsan River, Naju-si, Jeonnam-do, Korea
 
                       The existing flooding facility shown at the left has only blind gates and
                        the actuators to lift the gates. The new project plans to construct pump
                        gate system at the upstream of the existing facility and flap gates at
                        outside of the existing facility while the existing facility remains open.


                                 Bottom beam is positoned on the rebar for the bottom floor.


                                Side beam and upper beam are erected to form a guide frame.



                                 Pump gate assembly is arranged for Factory Acceptance Test.


                              Self descendable actuator is installed at the actuator test bench to
                               show the lifting capability.


                         Roller gate is installed with the main rollers guided within guide frame.


                                            Pump is mounted on the flange of roller gate.


                             Spindle is erected to connect the spindle bracket on roller gate and
                              the actuator at the top of the structure.


                                Actuator is lifted for the installation at the top of the structure.


                             Robochain is installed for the safe and easy handling of the power /
                              control cables from the pump.


                      Guide frames are installed at the outlet of waterway towards the outside river.


                              Three sets of flap gates are shown against the existing actuators at
                               the upper right of the above picture.


                          The installation of the actuators at the top of the structure is completed.


                            Building work for the control room at the top of the structure where
                            actuators and local control panel stay in in progress after the actuators
                            and the local control panel were installed in advance.


                                Pre-commissioning is in progress at the control room where
                                 local control panel and actuator are installed.


 
                          Front view shows the control room at the top and screen in the middle.
                               
                                   
 
 

                         