Pump Capacity : Ф1,200mm x 215cmm x 5mH x 4ea
Contract Period : 2008. 09. 01 ~ 2009, 05. 30
Location : Gang-dong, Ghimhae-city, Gyeongnam-do, Korea
Civil work starts with the excavation at the site.
Concrete work is composed of two stages. Main structure is exposed with
concrete form demolished after the completion of stage #1 concrete work.
Inspection is performed for the actuator during factory acceptance test.
Pump performance test is performed at the manufacturer's factory
during factory acceptance test.
Bottom beam is positioned before the stage #2 concrete work.
Guide frame is positioned before the stage #2 concrete work.
Surface of the bottom beam is shown after the drying of the stage #2
concrete work.
Roller gate is lifted from the trailer in order to be installed at the guide frame.
Pump is mounted on the roller gate by bolt tightening work.
Actuator is lowered cautiously to be installed on the base frame.
Rotary screen is installed at the inlet of pump gate for the safe pump operation
by filtering the debris.
Spindles connecting the actuator and pump gate are shown at the left and
control panel & platform for rotary screen are shown at the right.
Front view is shown with the rotary screen at the inlet of pump station.