Project : Taein Pump Station
Pump Capacity : Ф900mm x 100cmm x 4mH x 3ea
Contract Period : 2009. 04. 05 ~ 2010. 12. 31
Location : Taein-dong, Gwangyang-city, Jeonnam-do, Korea
Piling work is performed for reinforcing the ground on which pump gate is constructed.
Guide frame for hydraulic pump gate is erected prior to the civil concrete work.
Horizontal and inclinde conveyor belt is installed for moving the debris filtered by rotary screen.
Main body of the rotary screen in charge of filtering the debris is installed at the inlet of pump gate.
Pump is mounted on the gate prior to the installation of the pump gate.
Hydraulic power unit is erected to supply the hydraulic power to the cylinder in order to open/ close
the pump gate. Hydraulic cylinder is connected to the bracket of the pump gate.
Flap gate had been installed in order to prevent seawater from flowing back on high tide across
the road in front of the pump station. Revamping work is performed to replace the old flap gate.
The old flap gate is replaced with a new one at the spot neighboring seawater.