HASUH Pump Gate®, completed in Dewi Sri, Bali, Indonesia

Project                 : Dewi Sri Pump Gate
Pump Capacity    : Ф 800mm x 90cmm x 2.3mH x 2ea
Contract Period   : 2015. 05. 28 ~ 11. 30
Location              : Dewi Sri, Bali, Indonesia

A new project was awarded at the same Bali with the successful operation of the pump gate system which was completed at Kartika Plaza in Bali on 2013. A similar concept which was applied to Kartika Plaza project was used for the design. The space under the road was used for the pump gate facilities. Therefore, the space which was open during the construction had to be closed to be used as a road after the completion of the project.

                       Guide frame is now being installed at the early stage of the construction with
                        Civil Contractor's scope of work.



                               Engineer is busy finalizing the work for the local control panel.


                                              Local Authority visit to inspect the site.        


                             The inside water are discharged through pump with white foams at
                              the pre-commissioning test.


                         Training was performed for the operators who will be in charge of the
                          operation after the system will be turned over to the client.

             
                       Detail training regarding the local control panel operation is performed
                        at the container house with a prepared operation manual.

                
                        Covers are put over the space for the pump gate facilities to make the vehicles
                         pass on the covers as a road. Local control panel and hydraulic actuator are
                         seen through the transparent wall of the housing at the right.


                  The front view shows the generator for power supply at the right and the housing
                   at the left which contains local control panel and hydraulic actuator.