Pump Capaity : Ф 900mm x 110cmm x 2.3mH x 2ea
Contract Period : 2015. 06. 22 ~ 11. 19
Location : Pyeongdong-ro, Gwangsan-gu, Gwangju, Korea
Concrete work for the structure is made by Civil Contractor.
Guide frame is installed.
Two sets of gate are arranged after the fabrication.
Pump performance test is performed at the factory during the factory
acceptance test.
Inspection is performed by the Client at the site.
Pump gate is lifted during the actuator test at the site.
The view from the road shows the back side of the local control panel and the actuator.